UVU Paving Schedule for June 2015

The following paving projects are scheduled on UVU campus for the month of June 2015:

Mobilization and Traffic Control: 6/10-6/11
Lower Manhole Collars: 6/10
Edge Mill on Campus Drive: 6/11
Prep. Asphalt Patches: 6/12-6/15
Remove and Replace Concrete: 6/12-6/18
Install Inlet Box: 6/19
Asphalt Patching: 6/22-6/23
Asphalt Overlay Campus Dr.: 6/24-6/25
Remove/Replace Connector Road: 6/24-6/29
Cleanup, Striping, Misc.: 6/29-6/30

See full PDF at link below.

14227790 UVU Paving Schedule (2)

June 8, 2015 by UVU Blog

Browning Administration Building Elevator Out Of Service

The elevator in the Browning Administration building will be out of service for the next 8 weeks. The hydraulic system has failed and is being replaced. Elevators in the Pope Science and Woodbury Business Buildings can be used to access the second and first levels via the concourses. Access to the zero level will be limited to the exterior exit on the west end of the building near parking lot L-1. Thank you for your patience as we wait for the fabrication and installation of the new parts. Please call x8130 with any questions.

by UVU Blog

Limited Power Outage Scheduled For Aug. 15-16

A limited power outage has been scheduled for 800 South on Friday, August 15 at 6 p.m. through Saturday, August 16 at 5 p.m. This power outage is required to get the new Classroom building connected to the high voltage. If everything goes well this will be less than a 24 hour shutdown. The goal is to lessen impact before school starts.

Please be mindful that during the power shutdown, there will be no power to refrigerators, no HVAC (Heating, Ventilation, Air Conditioning), no power to fish tanks, limited security, etc.

Areas that will be WITHOUT power include:

GEAR UP
TRIO
Wolverine Testing Center / Athletics inside the building
Parking lots L3-10 +14 not lighted that night (Heavier University Police patrols planned in this area.)
Graphics sign for the freeway
Track field and scoreboard
Soccer field lights
Traffic light at Events Center Drive will be off. (Planned 3 way stop sign.)
Roadway lights along Sandhill Road

Areas that will be WITH power include:

McKay building
UCAS
Library
Street and crosswalk lights in front of McKay
Owls ball field

If you have questions please contact Denny Rucker at Extension 8326 or e-mail him with any of your concerns: RUCKERDE@uvu.edu.
PLEASE NOTE: There will be one additional outage in the late fall, closer to when the new classroom building is being turned over to UVU. The time has not been selected yet. But it will probably be on a weekend or holiday. More information as it becomes available.

Your support and understanding is greatly appreciated. Thank you!

August 8, 2014 by UVU Blog

UVU Roundabout Construction Update for July 23

Closure Notice:

The roundabout is schedule to close Friday, July 25 as early as 11:30 PM to accommodate the Orem Owlz traffic and reopen as late as 6AM on Monday, July 28 while crews pave.

The second closure is scheduled for August 1-3. On Friday, August 1, the roundabout will close as early as 11:30PM and reopen on reopen as late as 6AM on Monday, August 4.

Please use 400 West or 800 South as alternative routes.

Activities for the week of July 28:
Crews will begin to pour the concrete patch work on the roundabout.
Crews will continue the installation of electrical, signage and landscaping.
The bus stop on College Drive at 791 West will now be open.
Project Impacts:

Project impacts will include lane restrictions but one lane will remain open at all hours during construction except for the two weekend closures on July 25-27 and August 1-3.*

Pedestrian access will be limited, please be aware of sidewalk closed signs and use alternative routes.

Other impacts may include traffic shifts, night work, and weekend work.

Local residents and businesses may experience noise, dust, and vibration during the day.
*Activities are subject to change due to weather, supply, or equipment issues.

For more information, please contact the project team at 888-556-0232 or kandicedavis@utah.gov

July 23, 2014 by UVU Blog

UVU Roundabout Construction Update for July 18

Project Overview

The project will perform improvements at the roundabout entering UVU. This project will excavate and resurface the roadway and repair or replace sidewalks, drainage, curb and gutter. These modifications will better align traffic entering the roundabout and improve traffic flow.

The project is scheduled to complete in mid-August.

Project Activities

Please be aware that a new traffic pattern along the roundabout has been implemented and the speed has been reduced to 25 MPH.

Activities for the week of July 21:

College Drive is reduced to one lane while crews work on expanding the curb line. The bus stop has been rerouted to 735 W 1200 S, west of the University Gateway Apartments.

Crews will continue landscaping and laying asphalt along Campus Drive and Sandhill Road.

Crews will continue to pour the drainage, curb and gutter along Campus Drive.

Crews will be paving the roundabout the weekend of July 25-28. Please see the closure information below.
Closure Notice:

The closure schedule for July 18-20 has changed to July 25-27. The roundabout is schedule to be closed Friday, July 25 as early as 11:30 PM and reopen as late as 6AM on Monday, July 28.

The second closure is scheduled for August 1-3. More information to come.

Please use 400 West or 800 South as an alternative route.

Project Impacts:

Project impacts will include lane restrictions but one lane will remain open at all hours during construction except for the two weekend closures on July 25-27 and August 1-3.*

Pedestrian access will be limited, please be aware of sidewalk closed signs and use alternative routes.

Other impacts may include traffic shifts, night work, and weekend work.

Local residents and businesses may experience noise, dust, and vibration during the day.
*Activities are subject to change due to weather, supply, or equipment issues.

For more information, please contact the project team at 888-556-0232, or kandicedavis@utah.gov

July 18, 2014 by UVU Blog

Update On UVU Traffic Construction for July 10-27

Please be aware that traffic speed has been reduced to 25 MPH along the project alignment.

Activities for the week of July 10:

East College Drive will be reduced to one lane while crews continue to work on the curb line through mid-Aug.
Crews will begin landscaping and continue pouring asphalt along Campus Drive and Sandhill Road.
Motorists can expect some delay.

Advance closure notice for July 18-20 & July 25-27:
The roundabout is schedule to be closed Friday, July 18 as early as 7PM and reopen as early as 6AM on Monday, July 21.
The second closure is scheduled for July 25-27. More information to come.

Please use 400 West as an alternative route.

Project Impacts:

Project impacts will include lane restrictions but one lane will remain open at all hours during construction except for the two weekend closures on July 18-20 and July 25-27.*

Pedestrian access will be limited, please be aware of sidewalk closed signs and use alternative routes.

Other impacts may include traffic shifts, night work, and weekend work.

Local residents and businesses may experience noise, dust, and vibration during the day.

*Activities are subject to change due to weather, supply, or equipment issues.

July 11, 2014 by UVU Blog

Update On Campus Drive Roundabout Construction

Project Overview

The project will perform improvements and reconstruct the roundabout entering UVU. This project will excavate and resurface the roadway and repair or replace sidewalks, drainage, and curb and gutter. These modifications made will better align traffic entering the roundabout which will improve traffic flow.

The project is scheduled to complete in mid-August.

Project Activities

Crews have begun excavation of the asphalt and curb and gutter along Campus Drive and Sandhill Road, this will continue throughout the week of June 23.

Traffic is restricted to one lane entering and exiting the roundabout.

Activities for the week of June 23:

Crews will begin pouring concrete for the curb and gutter near the roundabout and the east side of Campus Drive. Motorists can expect some delay.

Project Impacts:

Project impacts will include lane restrictions throughout the project duration. One lane will remain open at all hours during construction.

Pedestrian access will be limited, please be aware of sidewalk closed signs and use alternative routes.

Other impacts may include traffic shifts, night work and right turn limitations from Sandhill Road and University Parkway.

Local residents and businesses may experience noise, dust, and vibration during the day.

June 20, 2014 by UVU Blog

Utah Valley University Maintenance Project Begins June 16

The Utah Department of Transportation (UDOT) and Utah Valley University (UVU) will begin maintenance on the roundabout at Sandhill Road and College Drive to improve traffic flow from University Parkway into the UVU campus.

The project is scheduled to begin the week of June 16. Project activities include asphalt removal and replacement, repairing or replacement of pedestrian ramps, sidewalks, and curb and gutter. This project will also add streetlights and landscaping. Construction is expected to be completed by mid-August.

“This roundabout is a major intersection with high traffic. Performing this maintenance now will help to improve traffic flow.” said UDOT Resident Engineer Travis Ackermann.

One left turn lane will be closed from eastbound University Parkway into the roundabout. Other construction impacts will include lane restrictions, traffic shifts, and some night work. Area motorists can expect some delay. Local residents and businesses may experience some additional noise, dust, and vibration.

For more information, the public is invited to contact the public involvement team at 1-888-556-0232 or www.uvu.edu.
Construction activities, dates and times are subject to change because of weather or delays.

June 11, 2014 by UVU Blog

Parking the first two weeks of Fall Semester

Students of UVU, as returning students may know, the first three weeks of Fall semester brings a large number of vehicles to the UVU campus. In order to help alleviate some of the parking congestion during the start of the semester, we have allocated some temporary overflow parking. There will be approximately 285 parking stalls located in the grass playing field to the east of Lot L10. The entrance to this temporary lot is located at the east end of L10. This overflow parking will require a purple permit (yellow is valid as well).

We have also added an overflow lot by the Health Professionals building at West Campus. This overflow lot will be primarily used to house the vehicles of the construction crews working on the Classroom Building and Student Life building projects. By moving the construction crews to this lot across the freeway, we are able to free up more space on campus for student parking.

Remember, during the first three weeks of the semester parking is tight on the main campus. We invite you to carpool, use public transportation, or other means to get to campus if at all possible. If you must drive a vehicle, please arrive early so that you are able to park and get to class as needed. Thanks, UVU Parking Services

August 9, 2013 by UVU Blog

July Fire Alarm Tests

Hi, Wolverines! Just wanted to give you a quick heads-up on some more fire alarm testing. The tests will take place:

Tuesday, July 23, 2 p.m. in the Computer Science Building
Wednesday, July 31, 11 a.m. in the LA Building and PE Building

Thanks for your patience!

July 17, 2013 by UVU Blog